Based on the cash flows shown in the chart below, compute th

Based on the cash flows shown in the chart below, compute the NPVfor Project Huron. Suppose that the appropriate cost of capital is 12percent. Advise the organization about whether it should accept orreject the project.Project Huron Time01234Cash Flow$12,000$2,360$4,390$1,520$3,300Based on the cash flows shown in the chart below, compute the IRRand MIRR for Project Erie. Suppose that the appropriate cost of capitalis 12 percent. Advise the organization about whether it should accept orreject the project.Project Erie Time012345Cash Flow$12,000$2,360$4,390$1,520$980$1,250